Risk type: Product size
Priority: 3
Risk factor:
Project completion will depend on the size of the product that have to fix the size of product. In our group, product size is uncertainty.
Probability: 60%
Impact:
Project completion will be delayed for each day that size of product is uncertainty.
Monitoring Approach:
- Using sprint planning to view the our milestone of the project.
- Using burn down chart to view the overall of the complete sprint.
Contingency plan:
Let out term to negotiate together and renew sprint plan in order to support new size of product.
Estimated resource:
Need more effort time available in sprint execute